Identity elements
Reference code
Name and location of repository
Level of description
Item
Title
A113567-3
Date(s)
- 1958-04-02 (Creation)
Extent
Name of creator
(1919-1980)
Content and structure elements
Scope and content
Another angle of the County-City Building construction in progress was taken on April 2, 1958, for Fentron Industries of Seattle. The taller structure is the ten story and penthouse central building. Scaffolding is in place, probably to put aluminum paneling over the exterior walls. The smaller wing would be eventually four stories tall and contain the law enforcement forces. It appears that the steel framework is up and most concrete floors poured. Parking would be provided in the vicinity of the piles of rubble and construction materials. Total cost of the project was under $10 million dollars. TPL-6568
Progress photographs; Building construction--Tacoma--1950-1960; County-City Building (Tacoma);